Optimizing the Design Process for Dredged Material Containment Area Dike Raisings Adjacent to Savannah River Harbor

2026-06-16T14:30:21-06:00October 26th, 2009|Tags: , |

The Savannah River Harbor requires periodic dredging to support commercial shipping traffic. These materials are disposed within a series of diked, dredged material containment areas (DMCAs) located on the eastern side of the Savannah River in Jasper County, South Carolina. Under mutual agreement, the US Army Corps of Engineers dredges the materials from the Port and disposes the materials in specific DCMAs identified by the Chatham County (Georgia) Engineers Office. Under this agreement, the Georgia Department of Transportation (GDOT) is responsible for the design and maintenance of the DCMAs which occupy 5,635 acres of land and are bounded by nearly 44 miles of front, back, and divider dikes. Part of this responsibility is to design and stage the requisite dike raisings to provide sufficient dredged materials storage capacity along an 18-mile long reach of the river. At the time of the project, the previous two dike raisings initiated a series of relatively small and localized slope stability failures. Relatively expensive short-term stability measures had to be developed by GDOT to provide the requisite storage capacity. GDOT's primary objective for the project was development of a strategy for optimizing dike construction and DMCA management so that cost-effective long-term dredge material containment could be provided.

Seismic Evaluation and Rehabilitation of the Lake Petit Dam

2026-04-06T11:38:44-06:00October 26th, 2009|Tags: , , |

One of the highest dams in Georgia is a compacted earth structure that serves as a water supply source and supports recreational activities for the Big Canoe residential community in North Georgia. During a routine dam safety inspection by the Georgia Safe Dams Program (GSDP), potentially excessive seepage was reported near the toe of the dam. A resulting detailed evaluation of the existing site conditions led to the development (by others) of a rehabilitation program involving the construction of a large toe buttress to minimize the adverse impacts of the seepage and to provide the requisite calculated factor of safety regarding static and seismic slope stability. The goal of the dam owners (Big Canoe Property Owners Association) was to evaluate alternatives to the toe buttress remedy that could achieve the required factor of safety and be more cost-effective and less environmentally intrusive. Geosyntec was retained by the dam owners to perform an independent third party review of the recommended remedy and assist in the identification of alternatives.

Sediment Remediation Program at Terry and Dupree Creeks, Brunswick, Georgia

2026-04-02T15:51:21-06:00October 24th, 2009|

This Dredge Spoil Area/Outfall Ditch site is located in coastal Georgia and consists of four source areas, three disposal areas and an outfall ditch. The sources border Dupree Creek, Terry Creek and the Back River. From 1948 through 1980, toxaphene was produced at a plant in Brunswick. During this period, wastewater was disposed directly into Dupree Creek. Interpretation of a 1971 aerial photograph showed a plume in Dupree Creek emanating from the outfall ditch.The U.S. Army Corps of Engineers (USACE) Savannah District has been involved in dredging Terry and Dupree Creeks since 1938. Dredged spoils had been disposed in three principal areas. The sediments dredged from Terry and Dupree Creeks were determined to be contaminated with toxaphene. The largest disposal area used by the USACE during this time was about 17 acres. The impoundment construction was such that sediment and water were disposed directly into the spoil area, and as the solids settled out of the dredge slurry, water was allowed to drain out of three weirs and back into Terry and Dupree Creeks.

Development and Implementation of Comprehensive Dredged Material Management Solutions for an LNG Facility, Savannah, Georgia

2026-04-02T15:50:27-06:00October 24th, 2009|Tags: |

Southern LNG (SLNG), a subsidiary of El Paso Corporation, needed to reopen its liquefied natural gas (LNG) terminal and ship off-loading facility at Elba Island in Savannah Harbor, Georgia.

Site Investigation and Remediation of Commercial/Industrial Property in Albany, Georgia

2026-04-02T15:50:27-06:00October 20th, 2009|Tags: |

Due diligence performed by Geosyntec for a former lease on behalf of the property owner indicated several potential Recognized Environmental Conditions (RECs) on site that warranted further evaluation. Geosyntec completed due diligence activities with the goal of managing the site assessment and subsequent remediation of chlorinated pesticides within the guidance of the Georgia Hazardous Sites Response Act (HSRA) and Georgia Hazardous Site Inventory (HSI). Once a site is listed on the HSI, significant costs can be incurred for regulation-required delineation of contaminants of concern to background concentrations (non-detect in the case of pesticides). Geosyntec successfully managed the project to avoid a HSI listing.

Air Permitting for Landfill Gas Beneficial Reuse Projects

2026-04-06T13:21:34-06:00October 19th, 2009|Tags: |

DeKalb County (DeKalb) wanted to expand its ability to use excess landfill gas (LFG) at its Seminole Road Municipal Solid Waste Landfill for beneficial use. DeKalb desired to: (i) construct a facility that would convert LFG to renewable natural gas (RNG); (ii) add a third engine to an existing Green Energy Facility (GEF) producing electric power through landfill gas-fired reciprocating internal combustion engines; and (iii) install a second flare to increase the capacity to burn LFG when both the GEF and the LFG to RNG were down. Because this facility is located in Atlanta's Nonattainment Area (NA) for ozone emissions, it is considered a New Source Review (NSR) NA major source. Therefore, it may only increase its nitrogen oxides (NOx) and volatile organic compounds (VOCs) emissions by 25 tons every five calendar years. Otherwise, costly and time consuming NSR NA permitting would be required. The site also is a Prevention of Significant Deterioration (PSD) major source for carbon monoxide (CO), and NSR PSD permitting would be required if CO emissions increased by more than 100 tons per year.

Go to Top