Implementation of an In Situ Thermal Desorption Remedy for Regulatory Site Closure
A portion of the privately owned "Route 44" property was excavated in the 1930s for fill for an off-site construction project. The resulting borrow pit was gradually filled with drums containing a variety of wastes. In the 1990s, the U.S. EPA conducted a series of site characterization studies, and in 2001, removed over 800 drums from the site. These removal activities were suspended after labels bearing the name of a nearby manufacturer were found on some of the drums. EPA then sent a Remedial Action letter to the corporate successor of that firm, who subsequently retained Geosyntec to provide oversight of the remaining drum removal activities, as well as to guide the site through the subsequent site assessment and remediation process and to ultimately achieve regulatory closure under the Massachusetts Contingency Plan (MCP).